{"data":{"id":"us-ak/as-34.35.068","jurisdiction":"us-ak","citation":"AS 34.35.068","heading":"Time periods for claiming liens.","body":"(a) If a notice of completion is not recorded by the owner as provided in AS 34.35.071, a claim of lien shall be recorded not later than 120 days after the claimant\n(1) completes the construction contract; or\n(2) ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's property.\n(b) If a notice of completion is recorded by the owner as provided in AS 34.35.071,\n(1) the following shall record a claim of lien or a notice of right to lien not later than 15 days after the notice of completion is recorded:\n(A) a claimant who has received advance notification of the date that the notice of completion is recorded as provided in AS 34.35.071(a)(2);\n(B) a claimant who has not given a notice of right to lien as permitted in AS 34.35.064;\n(2) the following shall record a claim of lien not later than the time specified in (a) of this section:\n(A) a claimant who records a notice of right to lien before or within the period specified in (1) of this subsection;\n(B) a claimant who has given a notice of right to lien but who has not received advance notice of the date that the notice of completion is recorded by the owner as provided in AS 34.35.071(a)(2).\n(c) A claim of lien is enforceable only if recorded by a claimant within the time specified in (a) or (b) of this section.","path":["Title 34. Property.","Chapter 35. Liens.","Article 2. Mechanics and Materialmen."],"source_url":"https://www.akleg.gov/basis/statutes.asp#34.35.068","current_through":"Alaska Statutes 2025 (34th Legislature, 2025-2026)","vintage":"","retrieved_at":"2026-09-02T06:18:42Z","sha256":"ca4badc3e64ba2eb918c54ca155f8519729030ff1922c17c863bb477714ac073","source_id":"us-ak","stale":false,"prev":"us-ak/as-34.35.067","next":"us-ak/as-34.35.069"},"notice":"GroundRules: Original legal text. Not legal advice."}