{"data":{"id":"us-ak/as-36.90.220","jurisdiction":"us-ak","citation":"AS 36.90.220","heading":"Optional contractual terms.","body":"Notwithstanding AS 36.90.210 and 36.90.230, the prime contractor or a subcontractor may negotiate and include in a public construction or public works subcontract a provision that permits\n(1) the prime contractor or a subcontractor to determine that part or all of a subcontractor's request for payment may be withheld for unsatisfactory performance under the subcontract; and\n(2) the prime contractor or a subcontractor to withhold payment for unsatisfactory performance without incurring an obligation to pay interest for late payment, if a notice complying with AS 36.90.240 has been previously furnished to the subcontractor and a copy of the notice is furnished to the contracting officer of the state or political subdivision.","path":["Title 36. Public Contracts.","Chapter 90. Miscellaneous Provisions.","Article 3. Public Construction Contract Payment."],"source_url":"https://www.akleg.gov/basis/statutes.asp#36.90.220","current_through":"Alaska Statutes 2025 (34th Legislature, 2025-2026)","vintage":"","retrieved_at":"2026-09-02T06:18:53Z","sha256":"60fc61447d3b5489364fef96e9f2378797cc8c15805effc6450d16c426f85c61","source_id":"us-ak","stale":false,"prev":"us-ak/as-36.90.210","next":"us-ak/as-36.90.230"},"notice":"GroundRules: Original legal text. Not legal advice."}