{"data":{"id":"us-ar/ark.-code-ann.-19-11-1406","jurisdiction":"us-ar","citation":"Ark. Code Ann. § 19-11-1406","heading":"Request for proposals","body":"(a) A request for proposals under this subchapter shall include without limitation the following: (1) The minimum qualifications of the construction manager-general contractor; (2) The procedures for submitting a proposal to the Arkansas Department of Transportation, the criteria for the evaluation of and selection of a construction manager-general contractor to perform preconstruction services, and the relative weight assigned for each criteria as indicated in a technical scoring matrix; (3) The form of the contract to be awarded for preconstruction services; (4) A listing of the types and scope of the preconstruction services that will be required; (5) The scope of the intended contract; (6) The budget limits for the transportation project and the preconstruction services; (7) The method of payment and structure of fees for the preconstruction services; (8) A requirement that the construction manager-general contractor submit relevant information regarding any licenses, registration, or credentials that may be required to construct the transportation project; (9) A requirement that the construction manager-general contractor provide evidence that establishes that the construction manager-general contractor is capable of obtaining the required bonding and insurance; (10) A requirement that the construction manager-general contractor submit information concerning the debarment or default from a federal, state, or local government transportation project within the past five (5) years; (11) A requirement that the construction manager-general contractor provide information concerning the bankruptcy or receivership of any of its members, including information concerning any work completed by a surety; (12) A requirement that the construction manager-general contractor provide evidence of competency, capability, and capacity to complete a transportation project of similar size, scope, or complexity; and (13) A prohibition that excludes a person or firm that has received compensation for assisting the department in preparing the request for proposals from submitting a proposal in response to the request for proposals or participating as a construction manager-general contractor team member. (b) A request for proposals under this subchapter shall not: (1) Require that the construction manager-general contractor have prior experience with any particular transportation project procurement method as a condition for submitting a proposal; and (2) Give any preference for any particular contract delivery method in the scoring of a proposal. (c) The department shall: (1) Send a written notice of award to the best-evaluated construction manager-general contractor; or (2) Send to all the construction manager-general contractors that submitted a proposal a written notice that all proposals have been rejected. Added by Act 2017, No. 809,§ 1, eff. 8/1/2017.\nreference for any particular contract delivery method in the scoring of a proposal. (c) The department shall: (1) Send a written notice of award to the best-evaluated construction manager-general contractor; or (2) Send to all the construction manager-general contractors that submitted a proposal a written notice that all proposals have been rejected. Added by Act 2017, No. 809,§ 1, eff. 8/1/2017.\n\n(a) A request for proposals under this subchapter shall include without limitation the following: (1) The minimum qualifications of the construction manager-general contractor; (2) The procedures for submitting a proposal to the Arkansas Department of Transportation, the criteria for the evaluation of and selection of a construction manager-general contractor to perform preconstruction services, and the relative weight assigned for each criteria as indicated in a technical scoring matrix; (3) The form of the contract to be awarded for preconstruction services; (4) A listing of the types and scope of the preconstruction services that will be required; (5) The scope of the intended contract; (6) The budget limits for the transportation project and the preconstruction services; (7) The method of payment and structure of fees for the preconstruction services; (8) A requirement that the construction manager-general contractor submit relevant information regarding any licenses, registration, or credentials that may be required to construct the transportation project; (9) A requirement that the construction manager-general contractor provide evidence that establishes that the construction manager-general contractor is capable of obtaining the required bonding and insurance; (10) A requirement that the construction manager-general contractor submit information concerning the debarment or default from a federal, state, or local government transportation project within the past five (5) years; (11) A requirement that the construction manager-general contractor provide information concerning the bankruptcy or receivership of any of its members, including information concerning any work completed by a surety; (12) A requirement that the construction manager-general contractor provide evidence of competency, capability, and capacity to complete a transportation project of similar size, scope, or complexity; and (13) A prohibition that excludes a person or firm that has received compensation for assisting the department in preparing the request for proposals from submitting a proposal in response to the request for proposals or participating as a construction manager-general contractor team member.\n\n(1) The minimum qualifications of the construction manager-general contractor;\n\n(2) The procedures for submitting a proposal to the Arkansas Department of Transportation, the criteria for the evaluation of and selection of a construction manager-general contractor to perform preconstruction services, and the relative weight assigned for each criteria as indicated in a technical scoring matrix;\n\n(3) The form of the contract to be awarded for preconstruction services;\n\n(4) A listing of the types and scope of the preconstruction services that will be required;\n\n(5) The scope of the intended contract;\n\n(6) The budget limits for the transportation project and the preconstruction services;\n\n(7) The method of payment and structure of fees for the preconstruction services;\n\n(8) A requirement that the construction manager-general contractor submit relevant information regarding any licenses, registration, or credentials that may be required to construct the transportation project;\n\n(9) A requirement that the construction manager-general contractor provide evidence that establishes that the construction manager-general contractor is capable of obtaining the required bonding and insurance;\nat the construction manager-general contractor submit relevant information regarding any licenses, registration, or credentials that may be required to construct the transportation project;\n\n(9) A requirement that the construction manager-general contractor provide evidence that establishes that the construction manager-general contractor is capable of obtaining the required bonding and insurance;\n\n(10) A requirement that the construction manager-general contractor submit information concerning the debarment or default from a federal, state, or local government transportation project within the past five (5) years;\n\n(11) A requirement that the construction manager-general contractor provide information concerning the bankruptcy or receivership of any of its members, including information concerning any work completed by a surety;\n\n(12) A requirement that the construction manager-general contractor provide evidence of competency, capability, and capacity to complete a transportation project of similar size, scope, or complexity; and\n\n(13) A prohibition that excludes a person or firm that has received compensation for assisting the department in preparing the request for proposals from submitting a proposal in response to the request for proposals or participating as a construction manager-general contractor team member.\n\n(b) A request for proposals under this subchapter shall not: (1) Require that the construction manager-general contractor have prior experience with any particular transportation project procurement method as a condition for submitting a proposal; and (2) Give any preference for any particular contract delivery method in the scoring of a proposal.\n\n(1) Require that the construction manager-general contractor have prior experience with any particular transportation project procurement method as a condition for submitting a proposal; and\n\n(2) Give any preference for any particular contract delivery method in the scoring of a proposal.\n\n(c) The department shall: (1) Send a written notice of award to the best-evaluated construction manager-general contractor; or (2) Send to all the construction manager-general contractors that submitted a proposal a written notice that all proposals have been rejected.\n\n(1) Send a written notice of award to the best-evaluated construction manager-general contractor; or\n\n(2) Send to all the construction manager-general contractors that submitted a proposal a written notice that all proposals have been rejected.","path":["AR Code","Title 19","Chapter 11","Subchapter 14"],"source_url":"https://oss-data-us.vaquill.ai/v2026.08/us_ar_statutes.parquet","current_through":"2026-08-14","vintage":"open-us-law v2026.08, retrieved 2026-09-14","retrieved_at":"2026-09-14T18:32:41Z","sha256":"2c59c4074c3f7367c21ee512878d0826d4e866fcef27104001de7685638fe1a9","source_id":"us-ar","stale":false,"prev":"us-ar/ark.-code-ann.-19-11-1405","next":"us-ar/ark.-code-ann.-19-11-1407"},"notice":"GroundRules: Original legal text. Not legal advice."}