{"data":{"id":"us-ct/conn.-gen.-stat.-16-50hh","jurisdiction":"us-ct","citation":"Conn. Gen. Stat. § 16-50hh","heading":"Restoration and revegetation of the right-of-way.","body":"As part of its supervision of construction activity in connection with any transmission line project, the Connecticut Siting Council may order such restoration or revegetation of the right-of-way occupied by the overhead transmission facilities approved with any transmission line project as it deems necessary to promote the long-term restoration of vegetation in portions of the right-of-way in residential areas where there has been a significant and material loss of screening as a result of clearing activities. Such restoration or revegetation orders shall include the requirement to establish vegetation that includes model pollinator habitat, as described in section 22-90b, and shall be consistent with all standards regarding required clearances between energized conductors and vegetation and all standards regarding minimum work distances for those working in proximity to conductors.","path":["TITLE 16. PUBLIC SERVICE COMPANIES","CHAPTER 277a*. PUBLIC UTILITY ENVIRONMENTAL STANDARDS ACT"],"source_url":"https://www.cga.ct.gov/current/pub/chap_277a.htm#sec_16-50hh","current_through":"Revised to January 1, 2026 (2026 Supplement to the General Statutes of Connecticut, applied over the base revision of January 1, 2025)","vintage":"","retrieved_at":"2026-09-06T19:07:01Z","sha256":"869b801e0561211cc473578227681a8c4c6fbe7d1b6f2f2e40ee5e97ec3c3d00","source_id":"us-ct","stale":false,"prev":"us-ct/conn.-gen.-stat.-16-50gg","next":"us-ct/conn.-gen.-stat.-16-50ii"},"notice":"GroundRules: Original legal text. Not legal advice."}