{"data":{"id":"us-ga/o.c.g.a.-13-10-70","jurisdiction":"us-ga","citation":"O.C.G.A. § 13-10-70","heading":"Liquidated damages for late completion and incentives for early completion.","body":"Public works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value. The terms of the liquidated damages provisions and the incentive provisions shall be established in advance as a part of the construction contract and included within the terms of the bid or proposal.","path":["TITLE 13 Contracts","CHAPTER 10 Contracts for Public Works","Article 1 General Provisions","PART 5 Project Completion Incentives in Contracts"],"source_url":"https://archive.org/download/gov.ga.ocga.2018/release86.2022.11/gov.ga.ocga.title.13.odt","current_through":"Release 86 (2022-11)","vintage":"Public.Resource.Org bulk O.C.G.A., Release 86 (2022-11), retrieved 2026-10-18","retrieved_at":"2026-09-17T18:57:07Z","sha256":"0ddc63690b2172949669ca88b833b96f2209176593bfe5a22cc1c7e65b19d865","source_id":"us-ga","stale":false,"prev":"us-ga/o.c.g.a.-13-10-66","next":"us-ga/o.c.g.a.-13-10-80","notices":[{"id":"pro-ga","title":"Georgia bulk release","text":"Georgia bulk files were republished by Public.Resource.Org under a public-domain dedication. GroundRules retains enacted text and strips editorial matter.","url":"https://archive.org/details/gov.ga.ocga.2018"}]},"notice":"GroundRules: Original legal text. Not legal advice."}