{"data":{"id":"us-il/30-ilcs-557-15","jurisdiction":"us-il","citation":"30 ILCS 557/15","heading":"Arbitration.","body":"A contractor and governmental entity may, by mutual agreement, arbitrate the contractor's entitlement to recover the actual increase in contract time or costs incurred because of a physical condition at the site. The judgment rendered may be entered in any court having jurisdiction over the matter.","path":["CHAPTER 30 FINANCE","Public Construction Contract Act."],"source_url":"https://www.ilga.gov/legislation/ILCS/details?ActID=543\u0026ChapterID=7\u0026ChapAct=FullText\u0026Print=True","current_through":"at least Public Act 104-790","vintage":"","retrieved_at":"2026-09-15T04:46:19Z","sha256":"1d367c0f6072ab3bd141d21cb4f13e501536b5a1461c566434e9a625f21bd81c","source_id":"us-il","stale":false,"prev":"us-il/30-ilcs-557-10","next":"us-il/30-ilcs-557-20"},"notice":"GroundRules: Original legal text. Not legal advice."}