{"data":{"id":"us-in/ic-8-1-7.9-25","jurisdiction":"us-in","citation":"IC 8-1-7.9-25","heading":"Commission's review of energy utility's estimated acquisition costs or project costs; recovery of costs","body":"Sec. 25. (a) The commission shall review an energy utility's:\n(1) estimated acquisition costs submitted under section 20(c)(1)(D) of this chapter; or\n(2) estimated project costs filed under section 23(b)(1)(D) of this chapter;\nas applicable.\n(b) If the commission approves, with or without modification, an energy utility's generation resource submittal or petition for approval of a project, the energy utility may recover:\n(1) acquisition costs; or\n(2) project costs;\nas applicable, that have been reviewed and found reasonable by the commission, with a return at the energy utility's weighted average cost of capital.\n(c) If the commission denies an energy utility's generation resource submittal or petition for approval of a project, the energy utility may recover planning costs that have been reviewed and found reasonable by the commission, without a return.\n(d) Absent fraud, concealment, or gross mismanagement, an energy utility may recover:\n(1) acquisition costs; or\n(2) project costs;\nas applicable, with a return at the energy utility's weighted average cost of capital, that the energy utility has incurred or contractually will incur in reliance on a commission order issued under this chapter.","path":["TITLE 8. UTILITIES AND TRANSPORTATION","ARTICLE 1. UTILITIES GENERALLY","Chapter 7.9. Expedited Generation Resource Plans and Large Load Customers"],"source_url":"https://iga.in.gov/ic/2026/Title_8.html#8-1-7.9-25","current_through":"2026","vintage":"2026","retrieved_at":"2026-10-04T20:08:46Z","sha256":"5430ab3fdaa39a3fa63551279ee743046299011f3ecbaf90a821e661ffcae002","source_id":"us-in","stale":false,"prev":"us-in/ic-8-1-7.9-24","next":"us-in/ic-8-1-7.9-26"},"notice":"GroundRules: Original legal text. Not legal advice."}