{"data":{"id":"us-in/ic-8-23-9-58","jurisdiction":"us-in","citation":"IC 8-23-9-58","heading":"Utility facilities; costs and delays due to facility relocations; contractor's right to compensation or expenses","body":"Sec. 58. (a) This section applies to a construction contract entered into by the department and a contractor after June 30, 2005.\n(b) The department may not include in a contract, or in any specifications or other documents that are a part of or incorporated in a contract, a provision that prohibits a contractor from receiving, or restricts the contractor in receiving, reasonable compensation or reasonable expenses directly related to unforeseen conditions encountered during the construction project as a result of:\n(1) a conflict with the facilities of a utility (as defined in IC 8-1-9-2(a)); or\n(2) delays due to the relocation of utility facilities;\nthat differ materially from the affected utilities or utility relocations specified in the contract documents.","path":["TITLE 8. UTILITIES AND TRANSPORTATION","ARTICLE 23. INDIANA DEPARTMENT OF TRANSPORTATION","Chapter 9. State Highway Contracts; General Powers"],"source_url":"https://iga.in.gov/ic/2026/Title_8.html#8-23-9-58","current_through":"2026","vintage":"2026","retrieved_at":"2026-10-04T20:08:46Z","sha256":"4dde1d8bc9fde254e91e4c9a16e36621b1e505bc6adde4954ea4440dfdbafadc","source_id":"us-in","stale":false,"prev":"us-in/ic-8-23-9-57","next":"us-in/ic-8-23-9-59"},"notice":"GroundRules: Original legal text. Not legal advice."}