{"data":{"id":"us-mt/75-20-208","jurisdiction":"us-mt","citation":"75-20-208","heading":"Certain electric transmission lines -- verification of requirements.","body":"(1) Prior to constructing a transmission line under 75-20-104(10)(a)(ii), the person planning to construct the line shall provide to the department within 36 months of the date of the public notice provided under 75-20-207, unless extended by the department for good cause:\n(a) copies of the right-of-way agreements or options for a right-of-way containing sufficient information to establish landowner consent to construct the line; and\n(b) sufficient information for the department to verify that the requirements of 75-20-104(10)(a)(ii) are satisfied.\n(2) The provisions of 75-20-104(10)(a)(ii) do not apply to any facility for which public notice under 75-20-207 has been given but for which the requirements of subsection (1) of this section have not been complied with.","path":["TITLE 75. ENVIRONMENTAL PROTECTION","CHAPTER 20. MAJOR FACILITY SITING","Part 2. Certification Proceedings"],"source_url":"https://mca.legmt.gov/bills/mca/title_0750/chapter_0200/part_0020/section_0080/0750-0200-0020-0080.html","current_through":"Montana Code Annotated 2025","vintage":"","retrieved_at":"2026-09-14T04:59:55Z","sha256":"2a1cdee8e0886bb56ca1a80f47e8b356165163bf0e3fb049d6111279c3de5f84","source_id":"us-mt","stale":false,"prev":"us-mt/75-20-207","next":"us-mt/75-20-209"},"notice":"GroundRules: Original legal text. Not legal advice."}