{"data":{"id":"us-ne/neb.-rev.-stat.-39-1345.02","jurisdiction":"us-ne","citation":"Neb. Rev. Stat. § 39-1345.02","heading":"Neb. Rev. Stat. § 39-1345.02","body":"A contractor shall not be held responsible, either during construction or after construction is completed, for damages which may result from or be due to inadequate, faulty, or insufficient design, plans, or specifications.","path":["NE Code","Chapter 39"],"source_url":"https://nebraskalegislature.gov/laws/statutes.php?statute=39-1345.02","current_through":"2026-08-14","vintage":"open-us-law v2026.08, retrieved 2026-09-14","retrieved_at":"2026-09-14T18:32:21Z","sha256":"4a9686e7fecc3109c93da2f0137ad5674503f74a363f1ec33a7cb8ce9abd8cc7","source_id":"us-ne","stale":false,"prev":"us-ne/neb.-rev.-stat.-39-1345.01","next":"us-ne/neb.-rev.-stat.-39-1346"},"notice":"GroundRules: Original legal text. Not legal advice."}