{"data":{"id":"us-ne/neb.-rev.-stat.-45-1209","jurisdiction":"us-ne","citation":"Neb. Rev. Stat. § 45-1209","heading":"Neb. Rev. Stat. § 45-1209","body":"The following provisions in any contract or subcontract for construction work performed within the State of Nebraska shall be against public policy and shall be void and unenforceable:\n\n(1) A provision that purports to waive, release, or extinguish rights to file a claim against a payment or performance bond, except that a contract or subcontract may require a contractor or subcontractor to provide a waiver or release of such rights as a condition for payment, but only to the extent of the amount of the payment received;\n\n(2) A provision that purports to make any state law other than that of Nebraska applicable to or governing any contract for construction within the state; or\n\n(3) A provision that purports to require that the venue for a court or arbitration hearing be held at any location outside of the state.","path":["NE Code","Chapter 45"],"source_url":"https://nebraskalegislature.gov/laws/statutes.php?statute=45-1209","current_through":"2026-08-14","vintage":"open-us-law v2026.08, retrieved 2026-09-14","retrieved_at":"2026-09-14T18:32:21Z","sha256":"0574a791c5488410499d3ba7f7780018bba81bed79009d8c6af2183d6c8acbd6","source_id":"us-ne","stale":false,"prev":"us-ne/neb.-rev.-stat.-45-1208","next":"us-ne/neb.-rev.-stat.-45-1210"},"notice":"GroundRules: Original legal text. Not legal advice."}