{"data":{"id":"us-nyc/n.y.c.-admin.-code-28-118.4.3","jurisdiction":"us-nyc","citation":"N.Y.C. Admin. Code § 28-118.4.3","heading":"§ 28-118.4.3 Timeframe for application.","body":"The application for the certificate of occupancy must be submitted within six months of the final construction inspection. The department may refuse to issue a certificate of occupancy where the final inspection was completed more than six months prior to such application.\n\n(L.L. 2021/126, 11/7/2021, eff. 11/7/2022)","path":["New York City Administrative Code","Title 28","Chapter 1: Administration"],"source_url":"https://files.amlegal.com/pdffiles/NewYorkCity/Admin/XML.zip","current_through":"Local Law 2026/135 (enacted August 31, 2026)","vintage":"","retrieved_at":"2026-09-06T02:48:57Z","sha256":"94880dc5fa6a58b46825c90ee449da208ec767ac13de690d6ab47836e0ee3012","source_id":"us-nyc","stale":false,"prev":"us-nyc/n.y.c.-admin.-code-28-118.4.2","next":"us-nyc/n.y.c.-admin.-code-28-118.5"},"notice":"GroundRules: Original legal text. Not legal advice."}