{"data":{"id":"us-oh/ohio-rev.-code-4906.212","jurisdiction":"us-oh","citation":"Ohio Rev. Code § 4906.212","heading":"Decommissioning estimated costs recalculation.","body":"The estimate of the total decommissioning costs of a utility facility, as described in division (B)(3) of section 4906.211 of the Revised Code, shall be recalculated every five years by an engineer retained by the applicant.","path":["Title 49 Public Utilities","Chapter 4906 Power Siting"],"source_url":"https://codes.ohio.gov/ohio-revised-code/section-4906.212","current_through":"2021-10-11 (Senate Bill 52 - 134th General Assembly)","vintage":"","retrieved_at":"2026-09-14T19:24:38Z","sha256":"480b2eb24e4757f3f60d88cd7374934f7700b705cef314524d431a9f07b39b40","source_id":"us-oh","stale":false,"prev":"us-oh/ohio-rev.-code-4906.211","next":"us-oh/ohio-rev.-code-4906.22"},"notice":"GroundRules: Original legal text. Not legal advice."}