{"data":{"id":"us-or/ors-279c.655","jurisdiction":"us-or","citation":"ORS 279C.655","heading":"Extension and compensation when work suspended.","body":"If a public contract is not terminated but work under the contract is suspended by an order of a contracting agency for any reason considered to be in the public interest other than a labor dispute or any third-party judicial proceeding relating to the work other than a suit or action filed in regards to a labor dispute, the contractor is entitled to a reasonable extension of the contract time and reasonable compensation for all costs resulting from the suspension plus a reasonable allowance for overhead with respect to such costs.","path":["07 - Public Facilities and Finance","26. Public Facilities, Contracting and insurance","Chapter 279C — Public Contracting - Public Improvements and Related Contracts"],"source_url":"https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html","current_through":"2025 Edition","vintage":"","retrieved_at":"2026-09-03T23:50:13Z","sha256":"d495cc84f17f30ae894e731763232cbdb20de27a1a88f60924479d3eec42c07b","source_id":"us-or","stale":false,"prev":"us-or/ors-279c.650","next":"us-or/ors-279c.660"},"notice":"GroundRules: Original legal text. Not legal advice."}