{"data":{"id":"us-or/ors-701.595","jurisdiction":"us-or","citation":"ORS 701.595","heading":"Failure to follow notice of defect procedure.","body":"If an owner compels arbitration or commences a court action against any contractor, subcontractor or supplier to assert a claim arising out of or related to the construction, alteration or repair of a residence located in this state and the owner has not followed the procedure set forth in ORS 701.565 and 701.575, the arbitrator or court must dismiss the arbitration or action without prejudice. The owner may not commence a new arbitration or action unless the owner follows the procedure set forth in ORS 701.565 and 701.575.","path":["17 - Occupations","52. Occupations and Professions","Chapter 701 — Construction Contractors and Contracts"],"source_url":"https://www.oregonlegislature.gov/bills_laws/ors/ors701.html","current_through":"2025 Edition","vintage":"","retrieved_at":"2026-09-03T23:50:17Z","sha256":"2dfb025fbda43f5ebdc07bd0f65d8a89f062450e54cecfb19a2ec1a30e7d1848","source_id":"us-or","stale":false,"prev":"us-or/ors-701.590","next":"us-or/ors-701.600"},"notice":"GroundRules: Original legal text. Not legal advice."}
