{"data":{"id":"us-ut/utah-code-73-5a-205","jurisdiction":"us-ut","citation":"Utah Code § 73-5a-205","heading":"Approvals void after one year if construction delayed -- Exceptions.","body":"(1) Any approval granted under Section 73-5a-203 is void one year after the date of approval if construction has not started.\n(2) The state engineer may extend the approval in one year increments:\n(a) upon a showing of reasonable cause for delay; and\n(b) provided state-of-the-art design criteria has not changed in the intervening period.","path":["Title 73 Water and Irrigation","Chapter 73-5a Dam Safety","Part 73-5a-2 Procedures for the Approval of Dam Construction Plans"],"source_url":"https://le.utah.gov/xcode/Title73/Chapter5a/73-5a-S205.html","current_through":"2026 General Session","vintage":"","retrieved_at":"2026-09-03T11:34:34Z","sha256":"272845b3331463d476b36aed5b24f30fbdbbc70c9ab80cbaa1af67fb30e67fd0","source_id":"us-ut","stale":false,"prev":"us-ut/utah-code-73-5a-204","next":"us-ut/utah-code-73-5a-301"},"notice":"GroundRules: Original legal text. Not legal advice."}