{"data":{"id":"us/25-cfr-170.474","jurisdiction":"us","citation":"25 CFR 170.474","heading":"Who conducts the project closeout?","body":"The following table shows who must conduct the TTP construction project closeout and develop the report.\nIf the project was completed by . . . then . . . and the closeout report must . . .\n(a) BIA The region engineer or designee is responsible for closing out the project and preparing the report (1) Summarize the construction project records to ensure compliance requirements have been met; (2) Review the bid item quantities and expenditures to ensure reasonable conformance with the PS\u0026E and modifications; (3) Be completed within 120 calendar days of the date of acceptance of the TTP construction project; and (4) Be provided to the affected Tribes and the Secretaries.\n(b) A Tribe Agreements negotiated under ISDEAA, or other appropriate agreements specify who is responsible for closeout and preparing the report (1) Meet the requirements of ISDEAA; (2) Comply with 25 CFR 900.130(d) and 131(b)(10) and 25 CFR 1000.249, or the Program Agreement, as applicable; (3) Be completed within 120 calendar days of the date of acceptance of the project; and (4) Be provided to all parties specified in the agreements.","path":["Title 25—Indians","CHAPTER I—BUREAU OF INDIAN AFFAIRS, DEPARTMENT OF THE INTERIOR","SUBCHAPTER H—LAND AND WATER","PART 170—TRIBAL TRANSPORTATION PROGRAM","Subpart D—Planning, Design, and Construction of Tribal Transportation Program Facilities"],"source_url":"https://www.ecfr.gov/api/versioner/v1/full/2026-08-25/title-25.xml","current_through":"2026-08-25","vintage":"","retrieved_at":"2026-08-27T02:24:59Z","sha256":"f90dbbd634b2323d68bcd07a618d4aa7a520b812fe37e5fd08d048967c3db86c","source_id":"us-cfr","stale":true,"prev":"us/25-cfr-170.473","next":"us/25-cfr-170.502"},"notice":"GroundRules: Original legal text. Not legal advice."}