{"data":{"id":"us/40-cfr-table-5-to-subpart-dddd-of-part-60","jurisdiction":"us","citation":"40 CFR Table 5 to Subpart DDDD of Part 60","heading":"Table 5 to Subpart DDDD of Part 60—Model Rule—Summary of Reporting Requirements 1","body":"Report Due date Contents Reference\nWaste Management Plan No later than the date specified in table 1 for submittal of the final control plan • Waste management plan § 60.2755.\nInitial Test Report No later than 60 days following the initial performance test • Complete test report for the initial performance test • The values for the site-specific operating limits • Installation of bag leak detection systems for fabric filters § 60.2760.\nAnnual report No later than 12 months following the submission of the initial test report. Subsequent reports are to be submitted no more than 12 months following the previous report • Name and address • Statement and signature by responsible official • Date of report • Values for the operating limits • Highest recorded 3-hour average and the lowest 3-hour average, as applicable, (or 30-day average, if applicable) for each operating parameter recorded for the calendar year being reported • If a performance test was conducted during the reporting period, the results of the test • If a performance test was not conducted during the reporting period, a statement that the requirements of § 60.2720(a) were met • Documentation of periods when all qualified CISWI operators were unavailable for more than 8 hours but less than 2 weeks • If you are conducting performance tests once every 3 years consistent with § 60.2720(a), the date of the last 2 performance tests, a comparison of the emission level you achieved in the last 2 performance tests to the 75 percent emission limit threshold required in § 60.2720(a) and a statement as to whether there have been any operational changes since the last performance test that could increase emissions • Any malfunction, deviation, or continuous monitoring system out of control periods information as specified in § 60.2770(k) through (o) • Fuel input information for energy recovery unit subcategory verification as specified in § 60.2770(p) §§ 60.2765 and 60.2770.\nEmission limitation or operating limit deviation report By August 1 of that year for data collected during the first half of the calendar year. By February 1 of the following year for data collected during the second half of the calendar year • Dates and times of deviation • Averaged and recorded data for those dates • Duration and causes of each deviation and the corrective actions taken • Copy of operating limit monitoring data and any test reports • Dates, times and causes for monitor downtime incidents § 60.2775 and 60.2780.\nQualified Operator Deviation Notification Within 10 days of deviation • Statement of cause of deviation • Description of efforts to have an accessible qualified operator • The date a qualified operator will be accessible § 60.2785(a)(1).\nQualified Operator Deviation Status Report Every 4 weeks following deviation • Description of efforts to have an accessible qualified operator • The date a qualified operator will be accessible • Request for approval to continue operation § 60.2785(a)(2).\nQualified Operator Deviation Notification of Resumed Operation Prior to resuming operation • Notification that you are resuming operation § 60.2785(b).\n1 This table is only a summary, see the referenced sections of the rule for the complete requirements.","path":["Title 40—Protection of Environment","CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY","SUBCHAPTER C—AIR PROGRAMS","PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES","Subpart DDDD—Emissions Guidelines and Compliance Times for Commercial and Industrial Solid Waste Incineration Units"],"source_url":"https://www.ecfr.gov/api/versioner/v1/full/2026-08-25/title-40.xml","current_through":"2026-08-25","vintage":"","retrieved_at":"2026-08-27T02:26:04Z","sha256":"0a883d68c9a621f5170c5bbd1f5c1e53a860901d7b083012f3450925020b6482","source_id":"us-cfr","stale":true,"prev":"us/40-cfr-table-4-to-subpart-dddd-of-part-60","next":"us/40-cfr-table-6-to-subpart-dddd-of-part-60"},"notice":"GroundRules: Original legal text. Not legal advice."}