{"data":{"id":"us/48-cfr-211.503","jurisdiction":"us","citation":"48 CFR 211.503","heading":"211.503 Contract clauses.","body":"(b) Use the clause at FAR 52.211-12, Liquidated Damages—Construction, in all construction contracts exceeding $900,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work. Use of the clause in contracts of $900,000 or less is optional.","path":["Title 48—Federal Acquisition Regulations System","CHAPTER 2—DEFENSE ACQUISITION REGULATIONS SYSTEM, DEPARTMENT OF DEFENSE","SUBCHAPTER B—ACQUISITION PLANNING","PART 211—DESCRIBING AGENCY NEEDS","Subpart 211.5—Liquidated Damages"],"source_url":"https://www.ecfr.gov/api/versioner/v1/full/2026-08-25/title-48.xml","current_through":"2026-08-25","vintage":"","retrieved_at":"2026-08-27T02:26:29Z","sha256":"18de2f02e7f41470a29a2ef084c3b264e2d8855062e335316ed49365e3d79f9f","source_id":"us-cfr","stale":true,"prev":"us/48-cfr-211.500","next":"us/48-cfr-211.602"},"notice":"GroundRules: Original legal text. Not legal advice."}