{"data":{"id":"us/48-cfr-511.503","jurisdiction":"us","citation":"48 CFR 511.503","heading":"511.503 Contract clauses.","body":"(a) Insert the clause at 552.211-12, Liquidated Damages-Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate (see FAR 11.501(a)).\n(b) Insert the clause at 552.211-13, Time Extensions, in solicitations and contracts for construction that includes the clause at 552.211-12.","path":["Title 48—Federal Acquisition Regulations System","CHAPTER 5—GENERAL SERVICES ADMINISTRATION","SUBCHAPTER B—COMPETITION AND ACQUISITION PLANNING","PART 511—DESCRIBING AGENCY NEEDS","Subpart 511.5—Liquidated Damages"],"source_url":"https://www.ecfr.gov/api/versioner/v1/full/2026-08-25/title-48.xml","current_through":"2026-08-25","vintage":"","retrieved_at":"2026-08-27T02:26:29Z","sha256":"7cf3d4189be7fd7d52404f22d0c7072c25570fa398c7f46f77b5e2594e5ca20b","source_id":"us-cfr","stale":true,"prev":"us/48-cfr-511.404","next":"us/48-cfr-511.600"},"notice":"GroundRules: Original legal text. Not legal advice."}