AS 09.45.887: Court action allowed after failure to repair or to settle.
Where this section sits in the code
- Title 9. Code of Civil Procedure.
- Chapter 45. Actions Relating to Real Property.
- Article 11. Action for Dwelling Design, Construction, or Remodeling Claims.
If the construction professional does not respond within the time required by AS 09.45.886, does not repair the defect to the satisfaction of the claimant within the time agreed under AS 09.45.886(1), does not provide an offer under AS 09.45.886(2), or serves a statement under AS 09.45.886(3), the claimant may bring an action against the construction professional for the claim described in the notice of claim without further notice.