Ala. Code § 39-2-10: Issuance of Proceed Orders by Awarding Authorities, Etc.
Where this section sits in the code
- Title 39 Public Works.
- Chapter 2 Letting, Execution, and Administration of Public Improvements Contracts by State Agencies Generally.
A proceed order shall be issued by the awarding authority within 15 days after final execution of the contract by the awarding authority, and execution by the Governor if his or her signature on the contract is required by law, unless both parties agree in writing to a stipulated extension in time for the issuance of a proceed order.