Ark. Code Ann. § 14-317-130: Estimate of work completed - Payment of contractors
Where this section sits in the code
- AR Code
- Title 14
- Chapter 317
It shall be the duty of the board to have the amount of work done by any contractor estimated from time to time, as may be desirable by the engineer selected by the board. The board shall draw its warrants in favor of the contractor for not more than ninety percent (90%) of the amount of work so reported, reserving the remainder until it has been ascertained that the work is completed according to contract and is free from liens.