CIV § 8180
Where this section sits in the code
- Civil Code - CIV
- DIVISION 4. GENERAL PROVISIONS [3274. - 9566.]
- PART 6. WORKS OF IMPROVEMENT [8000. - 9566.]
- TITLE 2. PRIVATE WORKS OF IMPROVEMENT [8160. - 8851.]
- CHAPTER 1. General Provisions [8160. - 8190.]
- ARTICLE 3. Completion [8180. - 8190.]
(a) For the purpose of this title, completion of a work of improvement occurs upon the occurrence of any of the following events:
(1) Actual completion of the work of improvement.
(2) Occupation or use by the owner accompanied by cessation of labor.
(3) Cessation of labor for a continuous period of 60 days.
(4) Recordation of a notice of cessation after cessation of labor for a continuous period of 30 days.
(b) Notwithstanding subdivision (a), if a work of improvement is subject to acceptance by a public entity, completion occurs on acceptance.