PCC § 10194
Where this section sits in the code
- Public Contract Code - PCC
- DIVISION 2. GENERAL PROVISIONS [1100. - 22355.]
- PART 2. CONTRACTING BY STATE AGENCIES [10100. - 19150.]
- CHAPTER 1. State Contract Act [10100. - 10285.5.]
- ARTICLE 6. State Agency Design-Build Projects [10187. - 10195.]
(a) If the department elects to award a project pursuant to this article, retention proceeds withheld by the department from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation of bids.
(b) In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld may not exceed the percentage specified in the contract between the department and the design-build entity. If the design-build entity provides written notice to any subcontractor that is not a member of the design-build entity, prior to or at the time the bid is requested, that a bond may be required and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the department and the design-build entity from any payment made by the design-build entity to the subcontractor.
Collected 2026-09-14T05:56:33Z. Source file · JSON