PCC § 9201
Where this section sits in the code
- Public Contract Code - PCC
- DIVISION 2. GENERAL PROVISIONS [1100. - 22355.]
- PART 1. ADMINISTRATIVE PROVISIONS [1100. - 9204.]
- CHAPTER 9. Claims and Disputes [9201. - 9204.]
(a) A public entity shall have full authority to compromise or otherwise settle any claim relating to a contract at any time.
(b) The public entity shall include provisions in a public works contract for timely notification of the contractor of the receipt of any third-party claim, relating to the contract.
(c) The public entity shall be entitled to recover its reasonable costs incurred in providing the notification required by subdivision (b).