Conn. Gen. Stat. § 13a-96: Payment to contractor under highway contract.
Where this section sits in the code
- TITLE 13a. HIGHWAYS AND BRIDGES
- CHAPTER 238. HIGHWAY CONSTRUCTION AND MAINTENANCE
- PART V. CONSTRUCTION AND MAINTENANCE
The commissioner shall pay any sum due any contractor under any contract awarded by him not later than sixty days after its completion and acceptance. After such sixty-day period, interest shall begin to run in favor of the contractor at the rate of six per cent per annum on the unpaid balance.
Collected 2026-09-06T19:07:00Z. Source file · JSON