Conn. Gen. Stat. § 16-50cc: Reconfiguration or burial of electric transmission facility.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 16. PUBLIC SERVICE COMPANIES
  2. CHAPTER 277a*. PUBLIC UTILITY ENVIRONMENTAL STANDARDS ACT

If legislation adopted on or after January 1, 2004, results in the reconfiguration or burial of a proposed facility described in subdivision (1) of subsection (a) of section 16-50i, all prudent costs incurred by an electric distribution company, as defined in section 16-1, associated with the reconfiguration or burial shall be deemed to be reasonable pursuant to sections 16-19 and 16-19e and shall be recovered by the electric distribution company in its rates.