Conn. Gen. Stat. § 42-158k: Retainage limitation. Payment by owner. Time limits.
Where this section sits in the code
- TITLE 42. BUSINESS, SELLING, TRADING AND COLLECTION PRACTICES
- CHAPTER 742b. CONSTRUCTION CONTRACTS
No construction contract may provide for any retainage in an amount that exceeds five per cent of the estimated amount of a progress payment for the life of the construction project. All retainage shall be paid by the owner not later than thirty days after the issuance of a certificate of final completion by the owner or the owner's authorized representative or not later than thirty days after the equivalent written acceptance of the construction project work by the owner.