D.C. Code § 40-303.13: When suit to be commenced.
Where this section sits in the code
- Title 40. Liens.
- Chapter 3. Mechanics, Materialmen, and Contractors.
- Subchapter II. Subcontractor’s Lien.
(a)
(1)
Any person with a lien and who has recorded a valid notice of intent shall only enforce the lien by:
(A)
Filing suit under § 40-303.08 to enforce the lien at anytime within 180 days after the date that the notice of intent is recorded in the land records; and
(B)
Recording, within 10 days of filing suit, a notice of pendency of action in accordance with § 42-1207(b) in the land records.
(2)
Failure to file suit within the 180-day period or to file timely a notice of pendency of action shall terminate the lien.
Collected 2026-08-29T05:44:07Z. Source file · JSON