7 Del. C. § 6098: Application shield.
Where this section sits in the code
- Title 7. Conservation
- Natural Resources
- CHAPTER 60. Environmental Control
- Subchapter VIII. Clean Air Act Title V Operating Permit Program
Except for sources required to have a permit before construction or modification under the applicable requirements of this subchapter, if an applicant has submitted a timely and complete application for a permit required by this title (including renewals), but final action has not been taken on such application, the source’s failure to have a permit shall not be a violation of this subchapter, unless the delay in final action was due to the failure of the applicant to timely submit information required or requested to process the application.
Collected 2026-09-05T23:02:09Z. Source file · JSON