21 GCA § 71109: Damages: Cost of Repairing.
Where this section sits in the code
- Title 21: Real Property
- Division 2 - Regulation of Real Property Uses
- Chapter 71: Underground Utility Damage Prevention
Any person who damages a utility line or roadway is subject to pay for all costs incurred by the operator to restore the utility or roadway to its original condition. The operator which has suffered damage, and has caused the repair of such damage shall present the contractor or person responsible for the damage with a bill for repair of the damage no later than sixty (60) days after the damage has been repaired.
If the operator of a utility fails to present the contractor within sixty (60) days after the damage has been repaired, the utility operator may not withhold excavating clearance for other projects for which clearance have been requested.
This Section shall apply to all government of Guam agencies performing work which results in the damaging of utility infrastructure as defined in this Act.
Collected 2026-09-27T04:14:28Z. Source file · JSON