620 ILCS 75/2-25: Prequalification to enter into public-private agreements.
Where this section sits in the code
- CHAPTER 620 AIR TRANSPORTATION
- Public-Private Agreements for the South Suburban Airport Act.
The Department shall establish a process for prequalification of offerors. The prequalification process shall: (i) provide a public notice of the prequalification at least 30 days before the date on which applications are due; (ii) set forth requirements and evaluation criteria in order to become prequalified; (iii) determine which offerors that have submitted prequalification applications, if any, meet the requirements and evaluation criteria; and (iv) allow only those offerors that have been prequalified to respond to the request for proposals.
The Department shall commence the prequalification process within 6 months after the effective date of this amendatory Act of the 103rd General Assembly.