815 ILCS 603/20: Retainage.

Read at publisher ↗
Where this section sits in the code
  1. CHAPTER 815 BUSINESS TRANSACTIONS
  2. Contractor Prompt Payment Act.

No construction contract may permit the withholding of retainage from any payment in excess of the amounts permitted in this Section. A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held. After the contract is 50% complete, no more than 5% of the amount of any subsequent payments made under the contract may be held as retainage.