IC 5-16-5.5-6: Payment of contractor; uncompleted minor items

Read at publisher ↗
Where this section sits in the code
  1. TITLE 5. STATE AND LOCAL ADMINISTRATION
  2. ARTICLE 16. PUBLIC WORKS
  3. Chapter 5.5. Retainage, Bonds, and Payment of Contractors and Subcontractors

Sec. 6. The contractor shall be paid in full including all escrowed principal and escrowed income by the state agency and escrow agent within sixty-one (61) days following the date of substantial completion, subject to IC 5-16-5. If at that time there are any remaining uncompleted minor items, an amount equal to two hundred percent (200%) of the value of each item as determined by the architect-engineer shall be withheld until said item or items are completed.