IC 5-16-8-3: Payment contingent upon compliance; recovery of payments made upon noncomplying contracts
Where this section sits in the code
- TITLE 5. STATE AND LOCAL ADMINISTRATION
- ARTICLE 16. PUBLIC WORKS
- Chapter 8. Steel Procurement for Public Works
Sec. 3. A public agency may not authorize or make any payments to a person under a contract containing the provision required by section 2 of this chapter unless the public agency is satisfied that such person has fully complied with that provision. Payments made to a person by a public agency which should not have been made as a result of this section shall be recoverable directly from the contractor or subcontractor who did not comply with section 2 of this chapter by the attorney general upon suit filed in the circuit court, superior court, or probate court of the county in which the contract was executed or performed.
Collected 2026-09-02T16:11:39Z. Source file · JSON