IC 5-32-5-2: Award of first tier subcontracts; prequalification of potential bidders
Where this section sits in the code
- TITLE 5. STATE AND LOCAL ADMINISTRATION
- ARTICLE 32. EMPLOYMENT OF CONSTRUCTION MANAGERS AS CONSTRUCTORS FOR PROJECTS
- Chapter 5. CMc Award of First Tier Subcontracts
Sec. 2. (a) A first tier subcontract shall be awarded to the bidder for that contract that would be awarded the contract under the applicable contract award standard.
(b) Before award of a first tier subcontract, the CMc may prequalify potential bidders based on written criteria established and published by the public agency. Otherwise, the applicable public works statute applies.
Collected 2026-09-02T16:11:39Z. Source file · JSON