IC 8-23-9.5-11: "Project"
Where this section sits in the code
- TITLE 8. UTILITIES AND TRANSPORTATION
- ARTICLE 23. INDIANA DEPARTMENT OF TRANSPORTATION
- Chapter 9.5. Project Delivery Methods
Sec. 11. (a) As used in this chapter, "project" means services provided using a two-phase contract with a CMGC or a PDB for preconstruction services and construction services to design, construct, alter, or repair:
(1) a state highway;
(2) a limited access facility (as defined in IC 8-23-1.1-27);
(3) a public highway (as defined in IC 9-25-2-4);
(4) a tollway;
(5) a bridge; and
(6) a passenger and freight railroad system.
(b) The term does not include a passenger railroad system that is operated by a commuter transportation district created by IC 8-5-15.