GroundRules
← Search the law
Kansas · Through 2025 legislative session

K.S.A. 66-1242: Same; recovery of capital expenditures for transmission facilities.

Read at publisher ↗
Where this section sits in the code
  1. Chapter 66.—PUBLIC UTILITIES
  2. Article 12.—MISCELLANEOUS PROVISIONS

Upon application, the commission shall provide for recovery of capital expenditures for construction or upgrade of any electric transmission line or appurtenances over a period of 15 years, unless: (a) The commission determines there is good cause to deny the application; or (b) recovery of capital expenditures for construction or upgrade of the transmission line or appurtenances is already provided for by tariffs and rates approved by the federal energy regulatory commission or its successors.

Collected 2026-10-15T06:25:36Z. Source file · JSON

Browse this collection