KRS 184.040: Examination of submitted plan of service by county road engineer.
Where this section sits in the code
- KRS Chapter 184
When a petition and plan of service have been submitted to the fiscal court as provided in
KRS 65.810 and 184.020 the fiscal court shall turn these documents over to the county
engineer for his consideration. The county engineer shall, within ten (10) days from his
receipt of such documents from the fiscal court, examine said documents, examine the
road proposed to be improved, or maintained, study the estimates of the cost and type of
surface proposed to be used, or study the estimates of the cost and type of the
contemplated maintenance and return to the fiscal court with recommendations of
approval or disapproval the documents theretofore delivered to him.