KRS 278.2219: Waiver or deviation from requirements of KRS 278.2201 to 278.2213.
Where this section sits in the code
- KRS Chapter 278
(1) Notwithstanding any provisions in KRS 278.2201 to the contrary, a utility may
apply to the commission for a waiver or deviation from any or all provisions of
KRS 278.2201 to 278.2213.
(2) The utility's application to the commission shall:
(a) Demonstrate the basis of the utility's need to be granted a waiver or deviation;
and
(b) Contain, if appropriate, documentation regarding the costs and benefits of
compliance with the provisions of KRS 278.2201 to 278.2213.
(3) The commission shall grant a waiver or de viation if the commission finds that
compliance with the provisions of KRS 278.2201 to 278.2213 is impracticable or
unreasonable. The findings of the commission shall be a final appealable order.