KRS 376.240: Perfecting a lien on funds due contractor from public authority.
Where this section sits in the code
- KRS Chapter 376
Upon the filing of the statement of lien provided for in subsection (2) of KRS 376.230 in
the county clerk's office and the delivery of an attested copy thereof to the public
authority making the contract for the improvement of any bridge, public highway or other
public property owned by the state or any county or city, and the filing with the public
authority of a signed copy of a letter addressed to the contractor or subcontractor at his
address given in the contract, with a post office receipt showing th at an attested copy of
the lien statement has been sent by the lien claimant to the contractor or subcontractor by
certified mail, return receipt requested or by registered mail, the claimant shall have a lien
superior to any lien subsequently perfected on any unpaid balance due the contractor
under the contract of improvement.