Kentucky · Snapshot 09/05/2026

KRS 446.030: Computation of time.

Read at publisher ↗
Where this section sits in the code
  1. KRS Chapter 446

(1) (a) In computing any period of time prescribed or allowed by order of court, or by

any applicable statute or regulation, the day of the act, event or default after

which the designated period of time begins to run is not to be included. The

last day of the per iod so computed is to be included, unless it is a Saturday, a

Sunday, a legal holiday, or a day on which the public office in which a

document is required to be filed is actually and legally closed, in which event

the period runs until the end of the next day which is not one (1) of the days

just mentioned. When the period of time prescribed or allowed is less than

seven (7) days, intermediate Saturdays, Sundays and legal holidays shall be

excluded in the computation.

(b) When a statute, regulation, or order of court requires an act to be done either a

certain time before an event or a certain time before the day on which an event

occurs, the day of the event shall be excluded in computing the time. If the

day thereby computed on which or by which the act is required to be done

falls on a Saturday, Sunday, legal holiday, or a day on which the public office

in which the act is required to be completed is actually and legally closed, the

act may be done on the next day which is none of the days just mentioned.

(2) If any proceeding is directed by law to take place, or any act is directed to be done,

on a particular day of a month and that day is Sunday, the proceeding shall take

place, or the act shall be done, on the next day that is not a legal holiday.