KRS 45.800: Prerequisites to transfer of money from contingency account or other
Where this section sits in the code
- KRS Chapter 45
sources.
(1) Except as otherwise provided in KRS 45.770(2)(b), prior to transferring funds from
any source to the allotment account of a capital construction project or major ite m
of equipment, the relevant entity head, or his designee, shall present to the Capital
Projects and Bond Oversight Committee, at least fourteen (14) days prior to the
committee meeting, for its review, specification of the amount of the proposed
transfer, documentation of the necessity for the transfer, and, with respect to capital
construction projects, documentation of:
(a) The amount already expended on the project prior to and during the current
biennium; and
(b) Any alterations made or planned in the project since its consideration by the
General Assembly during the most recent even -numbered-year regular
session.
(2) Within thirty (30) days after submission to the committee of a proposed capital
construction and equipment purchase contingency account t ransfer, the committee
shall determine whether the amount of the proposed transfer is reasonable and
consistent with KRS 45.770, whether the proposed transfer is necessary, and
whether any alterations made or planned in a project materially change the proj ect
as considered and authorized by the General Assembly. If the committee does not
approve a proposed transfer or other proposed action, the committee, unless the
Legislative Research Commission directs otherwise, shall promptly transmit its
findings and determination to the head of the entity that presented the proposal.
(3) If the committee does not approve a proposed transfer or other proposed action, the
transfer shall not be made nor the action taken unless the relevant entity head, or his
designee, shall:
(a) Revise the transfer or action to comply with the objections of the committee;
(b) Cancel the transfer or action; or
(c) Determine to make the transfer or take the action not approved by the
committee.
(4) The decision made by the relevant entity head, or his designee, under the preceding
subsection shall be communicated to the committee in writing within thirty (30)
days of the committee's not approving the proposed transfer or other proposed
action.
(5) The committee, unless the Legislative Resea rch Commission directs otherwise,
shall maintain records of its findings and determinations and the relevant entity
head's, or his designee's, report of his action on each proposed transfer from the
capital construction and equipment purchase contingency a ccount. If the committee
determines that the amount of a proposed transfer is not reasonable or is not
consistent with KRS 45.770, or that the transfer is not necessary, or if the
committee finds that any alteration in a project materially changes the proj ect as
considered and approved by the General Assembly, the committee's determination
and the action of the secretary of the Finance and Administration Cabinet, or other
appropriate entity head, on the transfer shall be transmitted to the appropriate
interim joint committees of the Legislative Research Commission and to the
General Assembly when next convened.
(6) The committee, unless the Legislative Research Commission directs otherwise,
shall maintain reports of purchases made under KRS 45.760(5), reports of transfers
made under KRS 45.760 to this section, reports of transfers made from the
emergency repair, main tenance, and replacement account, and a record of any
committee finding or recommendation relating to such purchases and transfers.
(7) The committee shall monitor the costs of state capital construction projects in
comparison with the costs of constructio n for the private sector to determine
whether the costs are comparable and, if not comparable, the reasons for any
difference. The committee shall consider contractors' charges to the state, land
acquisition costs, costs and availability of materials, cost and availability of labor,
and laws, regulations, and purchasing procedures pertaining to state capital
construction projects that are not applicable to construction for the private sector.
The committee's findings and recommendations shall be transmitted to the
appropriate interim joint committee of the Legislative Research Commission and to
the General Assembly when convened.