KRS 98.110: Awarding of contracts -- Commission may do part of work.
Where this section sits in the code
- KRS Chapter 98
All work done or supplies or materials purchased in carrying out the purposes of KRS
98.040 to 98.170, when involving an expenditure of five hundred dollars ($500) or more,
shall be by contract awarded to the lowest and best bidder. All bids or parts of bi ds for
any such work or supplies may be rejected by the commission. Any commission may,
with the consent of four (4) of its members, do any part of its work by day labor under
such conditions as it may prescribe, when such procedure is recommended in writi ng by
the superintendent of construction.