RS 48:255.4: Cost-plus contracts prohibited; exceptions
Where this section sits in the code
- TITLE 48. ROADS, BRIDGES AND FERRIES
Except for a duly certified emergency, no contract of the department shall be let on a cost-plus basis. Plan changes which cannot be negotiated and for which no item was provided in the original contract may be ordered on a cost-plus basis, if such basis was specified in the original contract as advertised.