35-A M.R.S. §4376: Commission and other agency action if certification not granted

Read at publisher ↗
Where this section sits in the code
  1. TITLE 35-A: PUBLIC UTILITIES
  2. PART 3: ELECTRIC POWER
  3. CHAPTER 43: NUCLEAR POWER GENERATING FACILITIES
  4. SUBCHAPTER 4: SPENT FUEL AND HIGH-LEVEL WASTE REQUIREMENTS

If the conditions of section 4374 have not been met, the commission may continue to receive and process applications for certification, but may not certify a nuclear power plant. Any other governmental entity which grants necessary permits, licenses, approvals or authorizations for construction of a nuclear power plant may process and grant those permits, licenses, approvals or authorizations, subject to the commission's granting of certification under this chapter.