Mich. Comp. Laws § 460.565: Transmission line; certificate required.
Where this section sits in the code
- MI Code
- Chapter 460
- Act Act-30-of-1995
Sec. 5.
An electric utility, affiliated transmission company, or independent transmission company shall not begin construction of a major transmission line for which a plan has been submitted under section 4 until the commission issues a certificate for that transmission line. Except as otherwise provided in section 9, a certificate of public convenience and necessity under this act is not required for constructing a new transmission line other than a major transmission line or for reconstructing, repairing, replacing, or improving an existing transmission line, including the addition of circuits to an existing transmission line.
Collected 2026-09-14T18:32:31Z. Source file · JSON