GroundRules
← Search the law
Montana · Through Montana Code Annotated 2025

69-14-605: Time for completion of crossing.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 69. PUBLIC UTILITIES AND CARRIERS
  2. CHAPTER 14. RAILROADS
  3. Part 6. Railroad Highway Crossings

It shall be the duty of a railroad company to construct a crossing ordered by the board of county commissioners of any county within 60 days after service of such order; provided, however, that in case any crossing shall be ordered requiring any extended period of construction, such additional time as is reasonably necessary to complete the same shall be allowed by the commission upon the proper application for such extension.

Collected 2026-09-14T04:58:26Z. Source file · JSON

Browse this collection