71-3-405: Limitations of actions to foreclose liens.
Where this section sits in the code
- TITLE 71. MORTGAGES, PLEDGES, AND LIENS
- CHAPTER 3. LIENS
- Part 4. Farm Laborers' Liens
All actions for the foreclosure and enforcement of the lien herein provided for must be commenced within 90 days from the filing of the lien.